Parade Circle Pathway Extension

Location:
Charlotte County, FL

Services Provided:
General Contracting

A² Group, Inc provided construction services for Charlotte County’s Parade Circle Pathway Extension and Inner Circle Connection project. The project was for the construction of an eight-foot wide asphalt multi-use path that is approximately 2,933 lineal feet (0.55 miles) in length at the south end of Parade Circle in Rotonda West. The path connected to an existing asphalt path at both ends and is the Inner Circle Connection (ICC) for the missing pathway section of Parade Circle.

GOAA Continuing Project and Program Management Service Contract

Location:
Orlando, FL

Services Provided:
Program and Construction Management

A² has a Continuing Program and Project Management Services Contract with the Greater Orlando Aviation Authority (GOAA), which includes the Orlando International Airport and the Orlando Executive Airport. We provide all services necessary for the management of the design and construction of both individual projects and programs.


Venice Parking Lot 3

Location:
Venice, FL

Services Provided:
General Contracting

A² provided general contracting services for an asphalt parking lot adjacent to the City of Venice Public Fishing Pier and beach access in Venice, Florida. The Parking Lot Site 3 improvements included clearing and grubbing, asphalt and base parking area, asphalt and base walking trail, concrete sidewalks and driveway, striping, landscaping, and site lighting.


Firing Range for Charlotte County Sheriff's Office

Location:
Punta Gorda, FL

Services Provided:
General Contracting

A² is providing construction services for a Firing Range for the Charlotte County Sheriff’s Office in Punta Gorda, Florida. The project is located on 5.25 acres consisting of 4 structures (Firing Range, Support Building, Control Room, and 3 Bay Garage). The Firing Range is composed of 12 – 50 yard shooting lanes, fully baffled with an associated control room and 3 Bay Garage. Additionally, the support building houses an armory, offices, conference rooms, and restrooms. Project consist of complete site development, lead reclamation of existing berms, perimeter high security fencing, concrete and structural steel structures, target systems for range, metal roofing, framing and drywall, mechanical, electrical, plumbing and associated landscaping/ irrigation.

John Young Parkway & Boggy Creek Road Mainline SR-417 Toll Plazas

Location:
Orlando, FL

Services Provided:
Construction Engineering and Inspection

Our firm provided Construction, Engineering and Inspections (CEI) services to the Central Florida Expressway Authority (CFX). This project included the widening of SR-417 at the toll plazas to accommodate two express E-Pass median lanes with open road tolling (ORT) and ITS in the northbound and southbound directions.

Design/Build SR-528/SR-436 Interchange Flyover and Cargo Rd. Improvement

Location:
Orlando, FL

Services Provided:
Construction Engineering and Inspection

Our firm served as a subconsultant on the CEI team for two projects under this contract: the SR-528/SR-436 Interchange Project and the Cargo Road Improvement Project. The work required for SR-528/SR-436 Project included design management and the new construction of a ramp flyover and bridge (both bridges comprised of steel box girders), roadway widening of SR-528, roadway and bridge widening of SR-436, ramp reconstruction, ramp widening, drainage improvements, lighting, signing, pavement marking and ITS. Other relevant aspects of the project included drainage infrastructure systems, land forms, native planting, traffic control, irrigation, maintenance of access for pedestrians and sediment control. The Cargo Road Improvement Project consisted of the demolition, removal and reconstruction of three-quarter miles of roadway. Improvements included excavation for a new drainage canal, earthwork and the construction of a double-barrel concrete box. A² had a leading role on the project with our Project Administrator.


John Land Apopka Expressway Construction (SR-414)

Location:
Orange County, FL

Services Provided:
Construction Engineering and Inspection

A² provided CEI services as a subconsultant for DRMP. The project provided for construction of 4.4 miles of new roadway form CR-437A to Hiawassee Road. The project consisted of new construction along with clearing and grubbing 300 acres; 4.1 million CY of excavation and 4.5 million CY of embankment; drainage, pond excavation and stabilization; base construction and Superpave asphalt; 11 bridge structures, 55,000 square feet of RE wall construction; highway lighting and signage; fiber optic installation; landscaping along the expressway; a mainline express toll plaza and four ramp toll plazas; and surcharge.

SR-528 & Narcoossee Interchange & Beachline Toll Plaza

Location:
Orlando, FL

Services Provided:
Construction Engineering and Inspection

A² provided Construction Engineering and Inspection (CEI) services on two Central Florida Expressway Authority (CFX) projects along SR-528 (Beachline Expressway): the conversion of the Beachline Main Toll Plaza and the reconstruction of Narcoossee Road Interchange. The Beachline Main Toll Plaza (SR-528) was converted into an express configuration. This task consisted of mainline roadway widening; the construction of a new entrance and exit ramps to access new cash lanes; and the expansion and modification of the mainline toll plaza in order to provide two E-PASS lanes in each direction. The Narcoossee Road Interchange reconstruction included the modification of the existing interchange to accommodate the six-lane section, raising the approaches for SR-528 from east of Goldenrod Road to east of Narcoossee Road. Two of the three span bridges werereplaced with two single span steel plate girder bridges. 

SR-826 Coral Way (24th St) & SW 8th Street Interchanges

Location:
Miami, FL

Services Provided:
Construction Engineering and Inspection

A² provided CEI services for FDOT District 6. The project included adding lanes and reconstructing the interchange at SR-826 (Palmetto Expressway) and Coral Way and at SR-826 and SW 8th Street, 12,000 LF of noise wall, approximately 2,000 LF of retaining wall and JPA relocation of 30” DIP WM along Tamiami Trail from Sta 1893 to 1901. This project reached completion nearly two months early on January 28, 2008 which entitled the contractor to a $4.6 million bonus. This project was also selected for the Florida’s Best in Construction Award for Partnering. 


Miami Dade Water and Sewer Rehabilitation

Location:
Miami, FL

Services Provided:
Engineering and Construction Support

A² provided Engineering and Construction Support Services on over $385,000,000 worth of work for the Miami-Dade County Water and Sewer Department.  The Department was in the process of rehabilitating its wastewater collection and treatment systems.  The system was anticipated to cost over $1 billion in order to meets its federally mandated completion goal. Our firm played an integral part in the achievement of this goal on various projects. The scope of engineering and construction services performed for the County includes civil engineering design, preparation and compilation of construction documents, bid solicitation, bid analysis and recommendations, contract award, document and cost controls, scheduling, and claims avoidance. 


Engineering & Construction Management for Miami Dade Public Works

Location:
Miami, FL

Services Provided:
Engineering Construction Management

A² provided engineering construction management services for the Miami-Dade Public Works Department. The range of services included full administration of construction contracts, inspection, technical assistance, claims analysis, estimating, CPM scheduling, and a provision of qualified personnel to supplement county staff in the monitoring of contractor work.


Miami Dade College Burn Building Training Facility

Location:
Miami, FL

Services Provided:
Construction Management at Risk

A² provided construction management at risk services for the construction of the Burn Building Training Facility, which is located at the North Campus of Miami-Dade College. The facility is composed of a two (2) story Fire Science Burn Lab that offers live fire training opportunities to new and veteran fire fighters. The 2,000 sq ft structure provides Class A and high tech LPG simulators with smoke capability. This project was completed three weeks ahead of schedule.   

Miami Dade College LEAP Library Renovation

Location:
Miami, FL

Services Provided:
Construction Management at Risk

A² was the construction manager at risk for Miami Dade College’s North Campus LEAP Project. The project consisted of renovations to the 40,000 SF existing library building to include new library adjunct labs for reading, writing, and math with related spaces on the second floor, and new faculty office on the first and second floor. The scope of work also included renovations for ADA compliance and the replacement of the Library building’s HVAC System. The library was open during construction, so special measures had to be taken not to interrupt students, faculty, and staff. This project was completed two weeks early.

Miami Dade College Restrooms Renovations

Location:
Miami, FL

Services Provided:
Engineering Design

A² provided CM at Risk services for Miami-Dade College’s Restroom Renovation for Buildings 5000 and 7000 on the North Campus. The objective of this project was to renovate ten restrooms through five stories in Buildings 5000 & 7000. Our responsibilities as Construction Managers At Risk included preparing a construction cost estimate, locating and contacting subcontractors, preparing pre-qualification packages, preparing Bid packages, as well as overall management of the project and document control.

FEMA Dorm Drainage Designs for DERM

Location:
Miami, FL

Services Provided:
Engineering Design

We provided engineering design services on various projects for the Miami-Dade Department of Environmental Resource Management (DERM).  Duties included surveying of prospective work sites and developing conceptual designs, permit application, and construction plans for large scale or complex projects such as new or existing stormwater drainage systems, restoration of filled or hydrologically altered wetlands, or modification of drainage canals, salinity control structure or their operation; roadway and drainage hazard mitigation design; and design services for FEMA funded projects involved restoring and replacing of drainage systems and repairing roadways damaged by major storms.


Engineering & Construction Management for DERM

Location:
Miami, FL

Services Provided:
Engineering Construction Management

A² provided engineering construction management services for the Miami-Dade Department of Environmental Resource Management (DERM).  The scope of work included services for the repair of infrastructure damage as a result of severe flooding that occurred during Hurricane Irene in October 1999 and another storm in October 2000.  We were also responsible for implementing hazard mitigation projects to reduce flooding and related property damage in the future.  The Federal Emergency Management Agency (FEMA) and the State of Florida’s Department of Community Affairs (DCA) and Miami-Dade County Stormwater Utilityauthorized funding for Miami-Dade County to address these damages.  As the construction managers, A² was responsible for overseeing and coordinating the work of design consultants, surveyors and construction contractors.

Miami Federal Courthouse

Location:
Miami, FL

Services Provided:
Construction Management

A² provided construction management services to Dick Corporation for the construction of the Federal Courthouse in Miami, which is approximately 557,000 gross square feet. The project included 16 district courtrooms and chambers along with space for the Clerk of the Court, Grand Jury Suites, Pre-trial Services, the U.S. Marshals Service office, Marshal Service sally port with secure corridors and detention cells; automated data processing area for probation, the U.S. Attorney and GSA Operational/Joint Use space for conference/training rooms; loading dock, trash and recycling rooms, mail room, dock office, security/fire life safety office, and storage space. The project also included 110 secure indoor parking spaces.

United Airlines Cargo Facility

Location:
Miami, FL

Services Provided:
Construction Management

A² provided construction management services for the construction of a cargo building facility at the Miami International Airport. The building is designed to house approximately 95,000 square feet of cargo area and approximately 12,500 square feet of cargo operations offices including conference and training facilities.


Taxiway Alpha 3 at the Naval Air Station

Location:
Jacksonville, FL

Services Provided:
Design & Build Services

A² was contracted by NAVFAV Southeast to provide design-build services for the repairs to Taxiway Alphas A/3 at the Naval Air Station located at Jacksonville, FL. The work entailed geotechnical exploration, design and construction to repair Taxiway A/3 pavement (3,000 SY) and drainage in accordance with Unified Facilities Criteria, Airfield and Heliport Planning and Design, and Pavement Design for Airfields and Surface Drainage Facilities for Airfields and Heliports. A²’s design was based on new airfield loadings anticipated for the NAS JAX mission (737 MMA, C17, C5, C40, etc) over the next ten years. This project was conducted in an active secure airport facility, on airside, which required continual coordination with airfield operation to avoid disruption to their daily work schedule. Work was performed during both daytime and nighttime. This project was completed two weeks ahead of schedule..